WebJul 11, 2016 · Building a new connection line between the KWA and Flint water treatment plant is expected to cost between $9 million and $12 million. Wright said the next phase of the KWA project will be to... WebMay 20, 2016 · The costs, as well as who would pay for it and who would build it, were underdetermined, he said, and “outside the purview of the KWA contract.” KWA attorney Kevin Kilby backed up Wright in...
About karegnondi
WebJun 22, 2016 · But as the state-appointed manager of Flint, Brown was backing the $285-million KWA project, well in advance of the Flint City Council. In his 2016 State of the State address, Snyder said:... WebApr 23, 2024 · Budget proposal jumps by $12 million, to $71 million. The City Council discussed the City’s 2024/2024 proposed budget. It was noted that there was a $12 … biting off more than he can chew
The Flint Water Crisis, the Karegnondi Water Authority and …
WebApr 25, 2016 · Flint city councilman Scott Kincaid stands by his support of going to KWA and says on the night of that vote, the council believed the city would stay with Detroit water until the KWA was ... WebFeb 8, 2016 · In June 2013, KWA began construction of its pipeline, which is expected to cost at least $285 million and bring water from Lake Huron to Flint as well as communities in Genesee, Lapeer, Sanilac ... WebApr 23, 2024 · The increase in the city’s proposed budget went from $59 million to $71 million. The City Administration and Department of Finance will present the budget, again, at Monday’s meeting, April 27 telephonically broadcast on YouTube. The public will have a chance to voice questions and comments about the budget at the May 11 council meeting. dataaps vlad for life insurance